Nalo Hydroelectric Project (360MW)
Client:
Indus Hydro Power (India) Private Limited
Services:
For providing consultancy services for Preparation of Detailed Project Report and Environment Impact Assessment/ Environment Management Plan preparation, Assistance in obtaining clearances from CEA/MoEF for the project and Technical Assistance in completion of Financial Appraisal by Lead Lender.
Details of the Project:
|
Location
|
Located in the Upper Subansiri District of Arunachal Pradesh
|
|
Total Catchment area
|
12,111 km2
|
|
Installed Capacity
|
4 x 86MW + 1x16MW = 360 MW
|
|
Dam
|
Concrete Gravity Dam, Height 160.11m above deepest foundation
|
|
Spillway
|
Surface Ogee with Sluice type
|
|
Diversion Tunnel
|
1 No, 14.00m dia, Horseshoe, Length 860.28m
|
|
Power Intake
|
Rectangular forebay type
|
|
Tailrace Tunnel
|
Size 5.5m dia, Horse shoe shaped, length Varies from 221.26m to 287.28m
|
|
Pressure Shaft
|
4 Nos, 4.5m dia, Type Underground with a vertical shaft
|
|
Powerhouse
|
Underground Powerhouse of size 129m (l) x 21m (w) 50.5m (h)
|
Present Status of the Project:
· Application for TOR (Terms of Reference) has been approved by MoEF in its meeting held on 11th November, 2011.
· Topographical Survey is in progress.
· DPR scheduled to be completed and submitted by May 2013.
|