Rongni Chu Hydro Electric Project (96 MW)
|
Client
|
Power Finance Corporation
|
|
Services
|
To provide Lenders Engineer Services
|
|
Location
|
Sikkim
|
|
Installed Capacity
|
2 x 48 MW
|
|
Barrage
|
120m long 35m wide and 14m high
|
|
Desilting basins
|
3 nos., 60m long, 18m wide and 7m high
|
|
Pressure Shaft
|
3.0m diameter having vertical/horizontal run of 415m
|
|
Surge Shaft
|
Restricted orifice type, 10m diameter and 87m height
|
|
Headrace Tunnel
|
Horse-shoe shaped of 12.6 Km length and 4.0m dia.
|
|
Powerhouse
|
Surface type 61.5m (L) X 45.75m (W) X 38.0m (H), 2 Nos. Pelton (Vertical Shaft type) of 48 MW each at a rated head of 406.60m
|
|
Switchyard
|
105m (L) X 77.5m (W) outdoor switchyard
|
|
Transmission Lines
|
Double circuit 220 KV, 2 Km length
|
Present Status of the Project:
· At present the project is in construction phase.
· As per the assigned work orders Phase-II (Implementation) is in progress i.e. the quarterly visits are made and the progress report is submitted to M/s Power Finance Corporation Ltd.
|
|