| PATIKARI HYDRO ELECTRIC PROJECT (2 X 8 MW) |
 |
| Developer: |
| Patikari Power Private Limited |
 |
Scope & Services:
E&M Works:
EPC Contact for the design, manufacture, supply, erection, testing and commissioning of E&M (Power Plant) equipment.
O&M supervision.
Main Civil Works:
Detailed Design,Construction Supervision &Project Management
|
 |
| Details of the Project: |
| |
| Location |
Mandi Dist, Himachal Pradesh |
| River |
BakhliKhad, tributary of Beas River |
| Catchment area: |
216 km2 |
| Diversion Weir |
27 m long Ogee type diversion weir |
| Desilting chambers |
2 no, 4.5 m width, 55 m long surface type |
| Head Race Tunnel |
1.8 m wide, 2.1 m high, 3614m long, D-shaped |
| Surge Shaft |
One number 6.0 m dia |
| Penstock |
One number 1.3 m dia, 715m long |
| Power House |
45m X 21.5 m, surface type |
| E&M Equipment |
Two numbers, 2 Jet, Horizontal Pelton Turbines operating at the rated net head of 356.3m, coupled to Synchronous Generators, each delivering 8 MW plus 15% continuous overload at its terminals. |
Present Status of the Project:
All Project components were successfully completed well within the specified Time Schedule. First Generating Unit was commissioned on 18th January 2008 and the Project was accorded the Commercial Operation (COD) w.e.f.6th February 2008.
Generation during Dec 2011 was 2.39 MU which is 43.4% of Design Energy of 5.51 MU for this month.
Generation during first eight months of current financial year 2011 was 48.74 MU which is 84.05% of the Design Energy (57.98 MU) for the corresponding period.
|
|

|
| |
 |
 |
|
| |
 |
|
|