| Teesta Stage III Hydroelectric Project (1200MW) |
| Client: Teesta Urja Limited |
Services:
Pre-construction stage investigations, preparation of Pre-Feasibility Report, preparation of Detailed Project Report, Preparation of tender documents and drawings, assistance in acquisition of clearances, assistance in bid and award of EPC Contract, Detailed Design, Construction services and Project Management.
|
| Details of the Project: |
| Location |
Dam site is located in Chungthang, North Sikkim district, Sikkim
|
| Installed Capacity |
6x200 MW = 1200 MW |
| Dam |
Concrete Face Rock Fill Dam, Height 60m, Length of the Dam at top 225.0 m |
| Diversion Tunnels |
One No. on left bank, 10.00 m dia horse shoe shape, Length 992 m |
|
Spillway Tunnels
|
2 No’s, 10.00 m diameter horse shoe shaped, 992m and 1181m long Spillway Tunnel on Left Bank and 1 No., 11.0m dia horse shoe shaped, 1357m long Flushing/Spillway Tunnel on right bank
|
| Chute Spillway |
2 bays of 11.00 m width, 300m long |
| Desilting chamber |
2 No’s, 320m long x 17.0 m wide and 23 m high |
| Head Race Tunnel |
One No. of length 13.8 km (From d/s of Desilting Chamber), size of 7.5 m dia, Horse Shoe shape |
| Surge Shaft |
Restricted Orifice type circular surge shaft, size 13 m dia, Height 155.0 m |
| Pressure Shaft |
Steel lined circular type, 2 Nos., Size 4 m/3.25 m/2.5 m diameter |
| Powerhouse |
Underground, Size of Machine-hall Cavern = 214.30m x 21.30m x 44.80m, Size of Transformer Cavern = 188m x 15.8 m x 16.0 m |
| Tailrace Tunnel |
Free flow tunnel type, Cross section area 8.2 m x 8 m (D-Shaped). |
|
|
Present Status of the Project:
· 75% of the Construction Supervision, Quality Assurance for Civil Works, Project Management & Contract Management services.
· 90% Detailed Design & Engineering including preparation for Construction drawings of all civil structures.
· 90% review of HM & EM designs.
|
 |
 |
  |
|
  |
|
| |
 |
|
|